| Item | Specification |
|---|---|
| Model / Type | 3LPE Coating Line for power plant and industrial process piping spools |
| Pipe Diameter Range | DN219-1220 mm (8 to 48 inch) |
| Typical Specification | external three-layer polyethylene on prefabricated spools, not only on line pipe |
| Pipe Spool Length | 3-12 m, including spools with flanges or fittings at one end |
| Pipe Wall Thickness | 6 to 40 mm |
| Coating Capacity | up to 500 m²/h at nominal wall thickness |
| Surface Preparation | shot blasting to Sa 2.5 or better, ISO 8501-1 |
| Wall Thickness Handling | heating time computed from measured wall thickness, not from diameter alone |
| Heating | intermediate frequency induction, 500 kW to 750 kW class |
| Extruder | with dedicated adhesive head and 1000 mm T-die |
| Spray Guns | 16 guns with four redundant positions and cartridge recovery |
| Powder Recovery | 95 percent or above with automatic filter cleaning |
| Cooling | water spray with recycle, air pre-cooling ahead of the spray for thick wall pipe |
| Conveyor | roller conveyor with flange clearance so a spool end can pass without fouling |
| Tolerance Control | coating thickness and cutback measured and recorded per spool |
| PLC and HMI | Well-known brand, recipe per diameter and wall thickness band, batch records for QA review |
| Operators per Shift | 4 |
| Dust Extraction | three-stage, sized for continuous shop duty |
| Warranty | 12 months machine, 24 months drive train |
| Certification | ISO 9001, Shandong First-Set Technical Equipment award |
![]()
![]()
![]()
![]()
![]()
Main Equipment List and specification
| No. | Name | Specification |
| A. Surface Cleaning Equipment | ||
| 1 | Steel pipe conveyor | Adjustable speed and angle, pipe uploading and unloading controlled by PLC |
| 2 | Shot blasting machine | |
| 3 | Cyclone dust collector | High efficient downwind cyclone dust removal |
| 4 | Impulse cartridge dust collector | |
| 5 | Centrifugal fan | |
| 6 | PLC control system | Automatic control of the line |
| B. Coating Equipment | ||
| 1 | Spiral pipe conveyor | Adjustable speed and angle |
| 2 | Induction heating machine | |
| 3 | Powder spraying device | Spraying thickness 80-800μm |
| 4 | Automatic feeder&dryer | |
| 5 | SJ-PE Extruder | |
| 6 | SJ-AD Extruder | |
| 7 | Adhesive extruder die mould | High quality die steel |
| 8 | PE sheet extruder die mold | High quality die stee |
| 9 | Adhesive/PE sheet coating device | Pressing roller with silicon coating and internal cooling |
| 10 | Environmental Protection Ventilation equipment | |
| 11 | Cooling Spray equipment | |
| C.Platform Equipment | ||
| 1 | Steel pipe platform | High quality |
| D.Groove Equipment | ||
| 1 | PE Beveling Machine | Steel brush disk, |
| 2 | Hydraulic Lifting and Turning Machinery | For lifting and turning the pipe |
| 3 | Hydraulic Equipment | |
The anti-corrosion coating processing line includes:
-steel pipe transmission system
-Internal and external shot blasting system
-dust collection system
-pipe heating system
-electrostatic spraying system
-PE coating system
-water cooling system
-end cutting system
-hydraulic and pneumatic system
-testing system
-electronic control system
Pipe is blasted to Sa 2.5 or better and the surface profile checked, since adhesion on PP systems is less forgiving of a weak profile. Internal air purging and end masking follow. Induction heating brings the wall to the coating window, which for polypropylene sits higher than for polyethylene and is held more tightly. Epoxy powder is applied electrostatically, the copolymer adhesive is extruded through its own head, and the polypropylene topcoat is laid by spiral wrap from the side extruder. Cooling is deliberately staged: the pipe passes through successive water spray zones rather than a single drench, so that the temperature gradient through the coating stays inside the limit the material can tolerate. Joint cutting, end bevelling and holiday detection close the cycle.
1. Pipe diameter: DN219-1220 mm (8 to 48 inch)
2. Processing capacity: ≥250m2/h
3. Cleaning level: ≥Sa2.5
4. Materials for production: epoxy powder, adhesive, polyethylene
Site supervision by 2 engineers over 15 to 25 days, timed to the shop's own commissioning rather than to a production milestone. Training focuses on the heating table by wall thickness and on mask control, since those two settings account for most of the variation between spools. English-language documentation includes layout, foundation, electrical, PID and manuals. Critical spares by air within 72 hours, with induction coil and mask parts held as stock items because a damaged mask stops the shop. Machine warranty 12 months, drive train 24 months.
![]()
![]()
![]()
Why Choose Qingdao Huashida
We build coating lines for pipeline mills and equipment for our own pipeline companies, and a large share of that work is thick wall and heavy section rather than thin line pipe. Our anti-corrosion equipment has been recognised on the Shandong Province First-Set Technical Equipment list, and our internal and external coating range covers the same diameters a prefabrication shop works in. That matters because heating a heavy wall spool efficiently is a different problem from heating line pipe of the same diameter.
---FAQ---
Q: Can the line coat spools that already carry a flange?
A: Yes. The conveyor is built with flange relief and the uncoated length is controlled by a mechanical mask, so the coating stops at the drawing dimension without an operator judgement call.
Q: How is heating controlled when wall thickness varies?
A: Wall thickness is measured at several points on the spool and the heating recipe is selected from that measurement. Diameter alone is not used, because it does not determine heat input on heavy wall pipe.
Q: Will the line fit our existing prefabrication bay?
A: The layout is quoted against your building, and in most cases it is the blast chamber and the cooling tunnel that set the length requirement. We ask for bay length and clear height before quoting.
Q: What is the typical coating thickness for plant piping?
A: Three-layer systems on plant piping usually run 2.5 to 3.7 mm total, but the figure is set by the service and the project specification, and we keep separate recipes where several specifications share a line.
Q: Does the line handle both thermal service and utility piping?
A: Yes, as separate recipes. Thermal service pipe and utility pipe can sit on different specifications, and the recipe library keeps them apart so the wrong one cannot be selected.
Q: How is a spool identified in the records?
A: Each spool carries its own release record with blast grade, coating thickness, cutback dimension and holiday test result, which is what the shop needs to hand the spool to erection.
Q: What is the operating crew?
A: Four operators per shift for this diameter range, including one on the mask and cutback stations.
Q: How long is installation and commissioning?
A: Installation and commissioning normally run 15 to 25 days, and it is scheduled to finish before the shop needs to release coated spools rather than before a fixed project date.